Construction Timeline

HELLO EVERYONE! WE WILL NOT BE CLOSED DURING THE RESTAURANT REHAB AND BREWERY ADDITION. IN FACT WITH THE ADDITION OF THE CLEMENT ROOM SEATS TO BE USED AS THE STATION AND OUR NEW BASIN BAR ON THE PATIO WE WILL HAVE 20 MORE STATION SEATS FOR OUR CUSTOMERS THAN WE DO NOW


MARCH 25TH

TEARING DOWN THE HOUSE PARTY LAST NIGHT THE STATIONS MAIN BAR WILL BE OPEN

BREWPUB BAR AND LOWER STATION WILL BE OPEN AS LOUNGE SEATING AND ENTERTAINMENT VENUE DURING RENOVATIONS

WE WILL STILL HAVE OUR USUAL ENTERTAINMENT SCHEDULE


MARCH 26TH

CONSTRUCTION BEGINS

THE RESTAURANT REMAINS OPEN, CLEMENT ROOM GRILLE WILL BE USED AS ADDITIONAL STATION SEATING BUT SERVE BREAKFAST AS USUAL

STATION ENTRANCE WILL CHANGE FROM TIME TO TIME, LOOK FOR TODAYS ENTRANCE


MARCH 27TH

CONSTRUCTION BEGINS ON NEW PARKING NEXT TO  CASCADE LODGE AND DEACHMAN AND SAWYER HOUSES

WE WILL HAVE 10 MORE PARKING SPOTS THAN WE ORIGINALLY HAD WHEN CONSTRUCTION IS COMPLETE

DURING PEAK SUMMER WE WILL OFFER FREE VALET PARKING AS WELL STATING IN 2013


MAY 1ST

BASIN BAR WILL OPEN ON THE PATIO


JULY 4TH

MAIN BAR REOPENS


SOMETIME IN JULY

NEW ENTRANCE, NEW LOUNGE AREA, GIFT SHOP WILL OPEN

RESTAURANT REVOVATIONSNS ARE COMPLETE, CLEMENT ROOM REOPENS FOR DINNER


AUGUST, SEPTEMBER & OCTOBER

CONSTUCTION WILL BE ISOLATED TO THE NEW BREWERY ONLY

BREWING EQUIPMENT ARRIVES


NOVEMBER &  DECEMBER

FIRST BREWS & FUNCTION ROOM OPEN

Leave a comment

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s

Blog at WordPress.com. Theme: Adventure Journal by Contexture International.

Follow

Get every new post delivered to your Inbox.

Join 50 other followers

%d bloggers like this: